Work to restore a heavily damaged nine-story apartment building at 50 Les Serdyuk Street in Kharkiv has been suspended. The building suffered extensive destruction during Russian shelling. Nearly 61 million hryvnias were allocated for the reconstruction, with the contractor having received 38.5 million hryvnias so far. The project is currently on hold pending a revision of the design plans and the search for additional financing.
This damaged residential tower is located in the Northern Saltivka neighborhood of Kharkiv. In 2022, the building was severely affected by fire and shelling, resulting in burnt apartments, damaged walls, roof, windows, and critical utility systems. Some residents began returning to their homes in 2023. In March 2025, the Kharkiv City Council signed a contract with the company PJSC 'Trest Zhytlobud-1' for emergency restoration work priced at almost 61 million hryvnias.
Progress and Challenges in Restoration
The contractor has partially repaired walls, windows, roofing, engineering networks, facade insulation, and the technical floor. However, important tasks remain incomplete, including:
- structural repairs;
- interior renovations;
- restoration of engineering systems;
- repair or replacement of elevators.
During the restoration, adjustments to the project documentation were commissioned to clarify technical solutions and the scope of work. By the end of October 2026, there were no funds available for continuing the repairs.
The contractor has been paid approximately 38.5 million hryvnias, covering around 63% of the contract’s total value. The final cost to complete the reconstruction will be determined after the updated plans are approved. The contract is valid until December 31, 2027. No specific timeline has been set for residents’ full return; completion dates will depend on revised project details and secured funding.
The 'Window of Restoration' initiative is part of the broader 'Public Investment Control' project, financially supported by the European Union. Essential remaining tasks include finishing repairs on damaged walls and other building elements, refurbishing individual apartments and common areas affected by fire and water damage, completing the restoration of utilities, and assessing the need to repair or replace elevators during the project revision phase.
The halt in restoring this nine-story building highlights the difficulties local authorities and contractors face in rebuilding infrastructure devastated by the war.
Securing extra funding and updating project documentation are critical challenges that may delay the completion of repairs and residents' return to their homes. The continuation of the 'Window of Restoration' project also reflects ongoing international support for Ukraine’s efforts to rebuild war-impacted communities.
While the restoration of the nine-story building at 50 Les Serdyuk Street faces significant funding challenges, there are ongoing efforts in the Northern Saltivka area to rehabilitate other residential buildings. For instance, another nine-story structure is making progress with plans to restore 252 apartments, highlighting the community's resilience in the face of adversity. To learn more about these developments, visit the latest updates on residential restoration efforts.